Upcoming – Surry Road (Rt. 172) Water Main Replacement

Starting next week, a water main replacement project will begin along Surry Road. This infrastructure upgrade will improve water service reliability and reduce the risk of future main breaks.

Project Details:

  • Location: The project will begin at the Bridge Hill intersection (convergence of Surry Road and Bucksport Road) and extend to approximately 148 Surry Rd.
  • Scope of Work: Crews will be excavating along the shoulder and, at times, into the roadway and adjacent streets to replace water lines.
  • Timeline: Construction is expected to continue through August, with potential to extend into September.
  • Work Hours: Monday through Friday, 6:00 a.m. to 5:00 p.m.

Traffic Impacts:

  • Expect single-lane closures, alternating traffic, and flaggers in place to direct vehicles safely through the work zone.
  • Delays are likely, especially during peak commute hours. Please plan accordingly and consider alternate routes when possible.

Informational Session:

  • April 30, 2025 at 6PM in the City Hall Council Chamber.
  • Opportunity for the public to ask questions about the project.

We appreciate your patience and cooperation as we update the water main. For project updates, visit https://www.ellsworthmaine.gov/ or follow the City’s Facebook page.

Additional questions can be directed to Water Department Superintendent Reggie Winslow at rwinslow@ellsworthmaine.gov or (207)667-8632.